Work will begin shortly to bury the current overhead medium and high tension power cables including those which cross the N-340/A-7 near the Hotel Beatriz in Fuengirola, so expect delays and/or diversions in this area.
The project will cost the Municipal Council €266,370 and is to be carried out by the company Melesur S.A with a completion period of two months. Such work does not fall under the mandate of the electricity company Sevillana, but the PGOU (all hail and genuflect) does require the construction of unerground electrical conduits in new development zones.
Any way, it will also improve the image of the area as well as improving safety.
The project includes the construction of 162 metres of conduits in calle Algorrobo, 132 metres in calle Mare Nostrum and 51 metres across the main road at km207.