Ronda awards contract for phase two of the Ciudad Deportiva

Ronda Council has awarded the contract for the second phase of work on the Ciudad Deportiva, which includes the construction of a grandstand with a capacity for 933 spectators.

The conract has been awarded to Obra Sport, S. L. and work could commence shortly. The contract is worth €1,120,125 and the completion time is nine months.

The original tender specifications envisaged a total cost of €1.4 million and a completion time of eighteen months. There were 17 bids for the contract, including four local companies and others from Granada, Sevilla and Pontevedra.