At the weekend, national PP member Celia Villalobos expressed her view that there was no way at all that the bidding process for the (long) proposed sewage plant in Nerja could begin before next year.
No delays to sewage plant
The Councillor for Infrastructure, José Alberto Tomé (PP), has announced that the planned Central Government spending cuts, amounting to €6,000 million, will not cause any further delays to the sewage plant in Nerja. What sewage plant?
PP spokesman dismissive of statement from Ministry of Environment
The spokesman for the ruling Partido Popular, José Alberto Tomé, has dismissed the recent statement from the Ministry of Environment that the sewage plant is a ‘priority’ as being ‘more of the same’, adding that no deadline has been set for action and that the whole process is in disarray due to the lack of communication between the PSOE controlled …
The residual water saga
The Secretary of State for Rural Affairs and Water, Josep Puxeu, said yesterday in Madrid that the future sewage plant in Nerja is ‘a priority’ and that the process to approve the preliminary work ‘continues to move forward’.
AEN urging action on innovative projects
The Asociación de Empresarios de Nerja (AEN), headed by the former socialist Mayor of Nerja, Gabriel Broncano, is sending letters to the various departments of the Málaga Provincial Government urging them to resolve the problems associated with the various projects considered vital for the town.
The sewage plant saga
The mayor of Nerja, José Alberto Armijo, has been responding to recent statements relating to the proposed sewage works, requesting that be it in phases, stages, episodes or chapters, the most important thing is to get the project started.
Proposal to build sewage plant in stages
A new twist in the perennial Nerja sewage plant project, which has been in the planning for over forty years, came as the Andalucian Water Agency proposed building the plant in stages so as to at least get it started, in some form, this year.
Doubts over sewage plant
The Councillor for Infrastructure, José Alberto Tomé (PP), has once again stated that the Council is fed up with being teased and constantly told that the contract for a sewage plant will be tendered ‘this year’, something which has been occurring regularly since 2001 when the Council made land available for the plant.
More delays to proposed sewage plant
As happens every year, it was promised that work on the proposed, and desperately needed, sewage works in Nerja would begin by the end of the year (2009). The Council were, as usual, sceptical, having heard the same promise so many times.
Council remains sceptical over sewage plant
The Nerja Council remains sceptical about continued announcements that work on the new (first and only!) sewage plant will begin before the end of 2010.